New Co-Generation System

The project involves the design, documentation, and delivery of a new standby generation and co-generation plant to support Crown’s existing Clarke Street Building, which houses administration offices, a fully automated wardrobe for staff, and retail and staff amenities.

New Co-Generation System – Clarke St, Southbank

Client Representative, Design Manager and Project Manager

Project:

New Co-Generation System – Clarke St, Southbank

Role:

Crown Resorts

EPMC, WSP

Client:

Crown Resorts

Partners:

Summary

The project involves the design, documentation, and delivery of a new standby generation and co-generation plant to support Crown’s existing Clarke Street Building, which houses administration offices, a fully automated wardrobe for staff, and retail and staff amenities.

This initiative utilises waste heat to provide heating hot water and domestic hot water to Crown’s Metropol Hotel. Key works included the installation of two 450 kVA Caterpillar gas-fired generators, complete with high-pressure heat exchangers and pumps, along with new switchboards to connect the generators to the existing infrastructure. A new Master Programmable Logic Controller (PLC) equipped with UPS and SCADA support was also implemented, alongside the installation of a fault-limiting inductor to manage contributions to Citipower infrastructure.

The project adhered to strict Citipower requirements for harmonic testing and monitoring, followed by the installation of a harmonic filtration system. Additionally, two new plant rooms were constructed: one for the new engines and associated equipment, and another for the switchboard installation to facilitate the interconnection of the generators to the Clarke Street Building. The project faced challenges such as executing cut-overs in a 24/7 operational facility, conducting simulated power failures on-site to test the new system, and negotiating with relevant authorities.

Works Included

Two 450 Kva Caterpillar Gas Fired Generators c/w high pressure heat exchangers and pumps

New Switchboards to serve both the gensets and to allow for the connection of the new plant to the existing Clarke St. building infrastructure

New Master Programmed Logic Controller (PLC) c/w new UPS and SCADA to support it

New Fault Limiting inductor that was required to be installed to limit fault contribution to Citipower infrastructure

Harmonic testing and monitoring to Citipower strict requirements

Subsequent install of Harmonic Filtration System to ensure that Citipower requirements were met on site

Construction of two new plant rooms, one to house the new engines and associated plant and equipment and one to allow
for the installation of a new switchboard to allow for the inter-connection of the gensets to the Clarke St

Challenges

Cut-overs and works taking place in 24 / 7 facility

Simulated power failures on site to test the new system

Negotiation with relevant authorities

For further information contact

daniel prince

Daniel prince

Director