Scada/PLC Upgrade – Crown Melbourne

Specialised was responsible for the design, documentation, and delivery of a comprehensive SCADA and PLC upgrade across Crown’s complex, specifically serving the tri-generation plant, which comprises six 1.1 MW gas-fired generators.

SCADA/PLC Upgrade at Crown Melbourne

Client Representative, Design Manager and Project Manager

Project:

SCADA/PLC Upgrade at Crown Melbourne

Role:

Crown Resorts

Systems Insight, EPMC

Client:

Crown Melbourne

Partners:

Summary

Specialised was responsible for the design, documentation, and delivery of a comprehensive SCADA and PLC upgrade across Crown’s complex, specifically serving the tri-generation plant, which comprises six 1.1 MW gas-fired generators. This project was crucial as the existing system, 18 years old, was outdated and no longer supported, with many parts rendered redundant.

Key tasks involved the installation of a new duplicated backbone Ethernet, spanning 2km to connect all existing and new PLCs, as well as deploying new Master and Standby Master PLCs. The project required a staged cut-over of 39 PLCs throughout the complex, the installation of new SCADA, and reprogramming of the load shed table, with the entire upgrade spread over 2.5 years to ensure meticulous planning and testing.

A significant challenge was managing and coordinating “Single Feeder Failures,” which entailed simulating power failures while the generators were either idle or operational. Additional difficulties included conducting staged cut-overs within a 24/7 facility, negotiating with relevant authorities for simulated shutdowns, and rigorous weekly testing of each PLC between 3 am and 5 am for an entire year.

This high-risk, high-profile project was essential for maintaining operational integrity within the organisation.

Works Included

Installation of new duplicated backbone Ethernet, 2km in length to link all existing and new PLC’s

New Master and Standby Master PLC

Staged cut-over of 39 PLC’s throughout the complex

New SCADA and re-programming of load shed table

Project staged over 2.5 years with planned testing

Managing and co-ordinating “Single Feeder Failures” which involves the simulation of power failure on the site whilst the gen-sets are idle (not running) and hot (running)

Challenges

Staged cut-overs and works taking place in 24 / 7 facility

Simulated power failures on site to test the new system – High Risk

Negotiation with relevant authorities for simulated shutdowns

Rigorous individual testing of each of the 39 PLC’s between 3am – 5am weekly for 12 months

High risk, high profile project within the organisation

For further information contact

daniel prince

Daniel prince

Director